LONDON insurer, the TT Club, together with global safety organisation ICHCA International and Port Equipment Manufacturers Association, have devised a set minimum safety recommendations for ship-to-shore quay cranes.
"The TT Club's global analysis of insurance claims by ports and terminals revealed that 34 per cent of the cost of asset-related claims worldwide were related to quay container cranes," said the joint statement.
The recommendations do not carry force of law, it said, nor can they be regarded as professional advice, and is independent of regulatory regimes, with which operators must comply, the statement said.
First, the two organisations feel that an anemometer should be installed in clear air at the top of the crane, giving an indication in the driver's cab, both audible and visual, that the safe operating wind limit has been reached.
They also recommend an audible alarm be installed to indicate to people on the berth that this limit has been reached.
"The anemometer shall be capable of recording well over the expected worst case windstorm. The wind speed, direction and time shall be recorded. The recommended maximum operating wind speed should be set at 22m/s [mean wind speed]," it said.
"Crane must not shutdown automatically, even if the alarm sounds continuously. This allows the crane to travel to the storm pin/tie-downs," the document said.
"Crane storm pins shall be installed at the centre of the crane under the sill beams on both waterside and landside and one or more corresponding locking positions on dock in distance reachable within the expected time to high wind condition.
"The storm pins, the mounting on the crane and also the pin sockets in the quay structure must all be designed to withstand the maximum forecast forces exerted.
"Substantial crane tie-downs on each corner and one or more corresponding locking positions on dock [should be at a] distance reachable within the expected time to high wind condition.
"The tie-down connections on the crane and also the anchor points in the quay structure must all be designed to withstand the maximum forecast forces exerted.
"Gantry drive braking system shall be designed to stop and hold the crane with a wind speed of 40m/s from behind.
"Design shall take into account uneven weight distribution so that the braking force transfers to the crane rails. This means there will be no wheel skidding under normal braking.
"Detection system to activate 'fast stop' of the lifting system and a system to absorb or isolate the kinetic energy in the lifting system, to prevent the excess of designed load in the lifting system.
"Temperature and smoke detection alarm systems inside the electrical control and machinery rooms should give audible and visual alarms in the driver's cabin, electrical and machinery rooms, outside the machinery house access door and on the landside sill beam.
Other recommendations include a "fully automatic fire suppression system mounted inside the electrical cubicles and a spring set of self-closing gates with positive means to open them.
"Any access gates to risk areas (ie, boom/trolley, cabin/boom etc.) shall be interlocked to prevent access when not in parked positions, or when in operation, and to prevent crane operation when open.
"System to measure, indicate and record the actual weight and eccentricity of each container is also needed as well as data to be capable of being transferred to the terminal operating system (TOS)," said the statement.
(Resource:http://www.shippingonline.cn)
|